The key points of bathroom decoration: first, wall tiles. Second, sanitary ware

Silver Crystal bathroom cabinet duoling hardware

key points of bathroom decoration:

first, wall tiles. Second, sanitary ware

(I) construction process

tiling wall tiles → Ceiling → Laying floor tiles → Install toilet, washbasin and bathtub → Install and connect the water supply and drainage pipe → Install lamps, sockets and mirrors → Install towel bar and other hardware accessories

1. Process flow of toilet

check the ground water outlet pipe → Align the nozzle → Level and align → Draw a good mark → Hole drilling → Apply putty → Cover the rubber pad → Screw on the nut, → Mark the two side holes on the back of the water tank, → Punching → Insert bolt → Twist firmly → The back water tank is hung flat and aligned → Screw on the nut → Install the drain elbow of the back water tank → Install the splayed door → Bend the lamp fork → Insert drift gate and splay gate → Tighten the nut

2. Technological process of washbasin

expansion bolt insertion → Twist firmly → Hang the basin pipe rack → Put the washbasin on the rack and level it → Water connection: washbasin → Straighten → Water supply connection

3. Bathtub process flow

bathtub installation: → Launching installation → Putty is tightly sealed → Water supply installation → Leveling and alignment

4 Technological process of shower

cold and hot water pipe orifices are leveled with test tubes → Measure the size of the nipple → Installed on the nozzle → The copper water inlet of shower is smeared with lead oil and wrapped with → Nut tightening → Fixed on the wall → The upper copper pipe is installed at the tee → Wood screws are fixed to the wall

5. The process flow of the body purifier

the door cover and nut of the mixing switch and the hot and cold water door are leveled, → Water gate installed → Install the nozzle rotating core door → Tighten the nuts at the outlet of cold and hot water valves → Tighten the nut on the mixing switch → Install three water gate covers → The magnetic basin is installed → When installing the nozzle → Install the lower water inlet → When installing the portable pull rod → Adjust the positioning

(II) construction essentials

1. Construction essentials of wash basin installation:

(1) wash basin products should be flat and free from cracks. The drain bolt shall have an overflow hole with a diameter of not less than 8mm

(2) when the drain bolt is connected with the washing basin, the overflow hole of the drain bolt should be aligned with the overflow hole of the washing basin as far as possible to ensure that the overflow part is unblocked. After inlaying, the upper end face of the drain bolt should be lower than the bottom of the washing basin

(3) bracket fixing bolts can be galvanized split bolts or galvanized metal expansion bolts of not less than 6mm (if the wall is perforated brick, expansion bolts are strictly prohibited)

(4) after connecting the washing basin with the drainage pipe, it should be firm and dense, and easy to disassemble, and the connection should not be open. The contact part between the washing basin and the wall shall be caulked with silicone paste

(5) if the sink drain trap and faucet are plated products, the plating shall not be damaged during installation

2. Installation essentials of bathtub:

(1) when installing the skirt bathtub, the bottom of the skirt should be close to the ground, and 250~300mm holes should be reserved in the floor at the drainage place for drainage installation, and manholes should be set in the wall at the drainage end of the basin

(2) the upper plane height of other bathtubs can be determined according to relevant standards or user needs. Then lay two brick foundations and install the bathtub. If a skirt wall is built on the side of the bathtub, manholes should be set at the drainage of the bathtub or on the drainage end wall

(3) the height of cold and hot water faucets or mixing faucets of various bathtubs should be 150mm higher than the upper plane of the bathtub. The chromium plating layer shall not be damaged during installation. The chrome plated cover shall be close to the wall

(4) the height of fixed shower and hose shower can be installed according to relevant standards or user requirements

(5) the upper surface of the bathtub installation must be checked and leveled with a level ruler, and no side inclination is allowed. The joint between the side of the upper opening of the bathtub and the wall shall be filled with sealing paste

(6) the connection between bathtub drainage and drainage pipe should be firm and dense, and easy to disassemble, and the connection should not be open

3. Installation points of toilet

1) the height of the angle valve installed on the water supply pipe is generally 250mm from the ground to the center of the angle valve. If the connected toilet is installed, it should be determined according to the height of the toilet inlet from the ground, but not less than 100mm. The center of the angle valve of the water supply pipe is generally 150mm to the left of the sewage pipe center or positioned according to the actual size of the toilet

2) the water tank of the low water tank toilet shall be fixed with galvanized split bolts or galvanized metal expansion bolts. If the wall is made of perforated bricks, expansion bolts are strictly prohibited, soft gaskets should be used between the water tank and the nut, and metal hard plates are strictly prohibited

3) the back of the water tank with the water tank and the one-piece toilet shall be no more than 20mm away from the wall

4) the installation of the toilet should be fixed with galvanized expansion bolts of not less than 6mm, and the toilet should be fixed with soft gaskets between the nut, and the sewage pipe should be 10mm above the ground

5) when installing the toilet, first coat the surrounding of the bottom drain with putty, then align the toilet drain with the sewage pipe orifice and slowly press it down tightly and fill it flat, then tighten the gasket nut to remove the extruded putty, fill it tightly with putty around the base, and immediately wipe it with a return wire or a rag

6) the height of the overflow pipe in the flushing tank should be 30~40mm lower than the wrench hole to prevent water from overflowing from the wrench hole when the water inlet valve is damaged

(III) precautions

1. Do not damage the waterproof layer. If the waterproof layer has been damaged or there is no waterproof layer, it should be waterproof first and undergo a 12 hour ponding and leakage test

2. The sanitary ware is firmly fixed and the pipe interface is tight

3. pay attention to the protection of finished products to prevent collision with sanitary ware